Guides / Order Planning
There is no honest single number, and the quotation you are comparing probably contains one anyway. The answer we publish on our own product pages is the one worth holding suppliers to: lead time is quoted per project and counted after the deposit and the drawing sign-off. Everything below is why that sentence is written that way, and what you can do to move your own date.
An order is a chain of five stages, not a duration. Deposit and drawing confirmation, production and in-line QC, packing and container loading, sea or land freight to destination, then on-site bolt assembly. The clock on the first stage only starts when two things exist: your deposit, which books the production slot, and your signed drawing, which releases the unit into build. Ask any supplier for a lead time before those two things exist and you are being quoted the middle of a sentence.
So the useful question is not “how many days”. It is “which of these five stages are yours, which are mine, and what date does each one carry”. That question gets different answers from our factory, and it gets answers you can check.
Most delays we see are not production delays. They are starts that never happened, because one of two things was outstanding.
The first start is the deposit. A production line runs on a schedule, and a slot on that schedule is booked rather than held. Until the deposit is received, your order has a price and no place in the queue. This is the point at which buyers who are still negotiating with a second supplier discover that the first supplier's slot has gone to somebody else, and the new slot being offered is later than the number they were quoted last week.
The second start is the drawing. Our product pages state it plainly: specifications shown are typical, and the final specification is confirmed against your drawing at quotation stage. That sentence is not a formality. A container house is made to a drawing — window and door positions, partition layout, electrical points, panel thickness, left-hand or right-hand opening — and the factory cannot cut, weld and assemble against a specification that is still moving. The distinction that catches people out is that the layout drawing and the production drawing are not always the same document. If the person signing off in your office assumes the technical drawing that follows is a detail they can review later, the order sits in the office rather than on the line.
Two dates, then. Deposit received, and drawing signed. A quotation that gives one number and does not say which of those two it counts from is not a schedule, and it is not comparable with the quotation beside it.
| Stage | What it needs from you | What moves this date |
|---|---|---|
| 1. Deposit & drawing confirmation | Purchase order, deposit payment, one decision-maker on the buyer side, and a drawing sign-off you are willing to hold | Payment clearing, revisions after sign-off, two departments inside your own company wanting different layouts |
| 2. Production & in-line QC | A frozen drawing, and answers on panel thickness, finish and electrical layout | Non-standard sizes beyond the frame module limits, custom panel thickness, inspection findings on a component held in stock |
| 3. Packing & container loading | The loading plan, and agreement on what is loaded in which container | Folded height and unit count per container, whether you consolidate with a second order, waiting for a matched container slot |
| 4. Sea/land freight to destination | The port or door address, and the import documents in the buyer's name | Vessel schedule and transhipment, peak-season space, and the destination side: customs clearance, unloading arrangements, road access to site |
| 5. On-site bolt assembly | A level, prepared base, power, and access for the delivery vehicle and lifting equipment | Model and site access, as our flat-pack page puts it; whether the base is ready when the truck is |
Only stage 2 and most of stage 3 are inside the factory's control. Stage 1 is usually the buyer's, stage 4 is a shipping line and a customs office, and stage 5 is decided on your site on the day the container arrives.
Ranked by how often we see each one, and by how much of it you control:
Buyers preparing for their first import usually assume the ocean is the schedule. It is not, once a container is booked and loaded. The sea leg is the part of the plan with the fewest moving parts, and its dates are published in advance by the carrier. Where time actually appears is at the two ends.
At the front end, everything between “we are interested” and a signed drawing is unstructured time. Nobody is tracking it, both sides are waiting for email, and it is the only phase that can be shortened for free by simply deciding faster. Buying the first order on a ten-day decision cycle instead of a six-week one is a real reduction in delivery date, and it costs nothing.
At the back end, the container arrives and the problem becomes physical: a delivery vehicle that cannot reach the plot, a base that is not finished, lifting equipment that is not on site, or a crew whose own calendar was planned around the container arriving on the original date. Our own product pages describe on-site assembly in a few words — the bolted frame goes together with a small crew, and the time depends on the model and the site access. Those two variables are the ones to plan for, and they are settled by a site visit before the order is placed, not after.
Four requests turn a lead time into a plan. They work with any supplier, and a supplier who cannot answer them is telling you something.
Then compare quotations on the same axis. Two suppliers quoting the same price with different stage dates are not offering the same product, and the difference is usually visible in the drawing stage: the supplier with a documented approval cycle quotes a date it can hold, and the other quotes a date it hopes to.
Six things are enough for us to confirm the model, the specification and a stage-by-stage schedule in the same reply:
With those, the reply states the stages with dates, which stage the dates are counted from, what we need from you and by when, and the price — on the same document.
The detachable container range publishes the five-stage loading and lead time sequence on the product page, the flat-pack range carries the standard sizes and panel specification, and the inspection process explains what is checked in-line during stage two rather than only before loading.
There is no single number we are willing to publish, and any supplier quoting one number for every order is describing their average rather than your order. The caliber we publish on the product pages is that lead time is quoted per project and counted after the deposit and the drawing sign-off, because an order is a chain of five stages and only part of that chain sits inside the factory.
Twice, and both starts are needed. The deposit books your slot in the production schedule, and the signed drawing releases the unit into build. If one of the two is outstanding, the order has a price but no date, and the date you were quoted last week may already belong to another buyer.
Deposit and drawing confirmation; production and in-line QC; packing and container loading; sea or land freight to destination; and on-site bolt assembly. The same five-step sequence is published on the detachable container product page, and each step has its own inputs and its own delays.
The first one. A drawing revision after sign-off is the most common cause of a slipped date, because components are cut against the signed version. The second most common is a buyer-side approval chain with several reviewers and no single person authorised to sign.
No. Once a container is booked and loaded, the sea leg is the most predictable part of the whole order, because carriers publish their schedules. The variability sits before the container is sealed and again at the destination, where customs clearance, unloading arrangements and site access are decided.
Ask for the five stages with dates, written on the quotation, and ask which stages are inside the factory and which are the buyer's to deliver. A stage list with dates can be measured as the order moves. A single duration cannot, which is why so many first-import disputes are about what the original number meant.
Not by asking for a shorter number. It can be shortened by freezing the drawing before production is scheduled, paying the deposit so the slot is real, choosing specifications that are already on the line, and where the destination is flexible, taking the first container slot offered rather than a later one that suits a preferred vessel.
A level, prepared base, power, and access for the delivery vehicle and any lifting equipment, plus a small crew for the bolted frame. As our flat-pack page states, the time depends on the model and the site access — which is why the site visit belongs before the order, not after the container has arrived.