Detachable container house installation: what has to be ready before the panels arrive

A detachable container house is bolted together on site, not welded. The frame is hot-dip galvanised steel with bolted detachable connections, the panels are sandwich panels that fix into that frame, and the whole thing arrives flat-packed: four sets in a 20 ft container, eight in a 40 HQ for the standard unit. So the installation question is not “who can weld it” but “is the base, the lift, the drawing and the crew ready on the day the container is opened”. This page takes those four in order, then the services connection, and finishes with the checklist worth having on site.

Quick answer

A detachable container house is installed in four operations: a level drained base, a lift of the frame sections onto it, a bolt-up in the sequence on the drawing, and the panels fixed into the frame with the services connected. No site welding is involved in the structure, so no welder and no hot work permit are needed for it. What the job does need is a base built before the container arrives, lifting equipment chosen on the unit weight at the working radius, and the assembly drawing on site rather than in an email inbox.

The failure mode is almost never the assembly itself. It is a base that was poured two days late, a crane that was booked for the wrong day, or panels standing in the wind because the frame was not bolted up yet.

Where “installation” sits in the order

On our own detachable container house page the order runs in five steps, and only the last one happens on the buyer's site. That split matters, because it means the site programme starts on the day the container lands, not on the day the order is placed.

  1. Deposit and drawing confirmation. The unit layout, the door and window positions, the panel core and the services scope are fixed against a drawing before anything is cut.
  2. Production and in-line QC. Frame members are cut and galvanised, panels are cut to the layout, and the unit is checked as it is built, not after it is packed.
  3. Packing and container loading. The unit is dismantled into frames and panels and packed flat, with the loading plan confirming the set count for that order.
  4. Sea or land freight to destination. This is the part of the schedule that the buyer does not control and the customs broker does.
  5. On-site bolt assembly. The only stage that needs a base, a lift and a crew. Everything this page describes lives here.

Because the unit travels as a kit, the buyer's site work is assembly and not construction: there is no concrete pour inside the scope, no structural steel erection in the conventional sense, and no wet trades beyond making the services connection good.

1. The base: it has to be flat, drained and ready first

The base does three jobs: it carries the unit, it holds the frame in one plane, and it keeps water away from the floor. On our standard build the floor is a cement fibre board over a steel joist, so standing water under the unit is a floor problem within a season, not a cosmetic one.

Footings are designed against the ground conditions under EN 1997-1, the geotechnical part of the Eurocodes, and the two inputs to that design are the unit weight and the imposed floor load. Both come from the supplier for the specific unit, and both should be requested with the quotation rather than assumed. What the base is made of is a local decision: cast-in-situ pad or strip footings, precast blocks, or screw piles. On a site with a defined service life, screw piles come out again; on a site that will be built over, a slab may be the cheaper choice even though it is heavier work.

Level is the part buyers underestimate. A bolted modular frame does not absorb an out-of-level base the way a site-built frame can: it shows up as doors that will not close cleanly, windows out of square, and panel joints that will not pull up. Ask the supplier for the level tolerance the frame is set out to, and check the base against it with a level and a string line across both diagonals of each footprint before the container is opened. Fixing a base is a day. Fixing it after the units are bolted is a week.

Standard unit footprints the base has to suit
UnitExternal sizeFootprint
20 ft standard6058 × 2438 × 2591 mm14.77 m²
40 ft12192 × 2438 × 2591 mm29.72 m²

Sizes are the standard build on our product page; custom sizes are available and change the base. The footprint column is the external size multiplied out, not a usable floor area: internal area is smaller by the wall thickness.

Two more base items belong in the same conversation. The first is anchoring: wind action is calculated under EN 1991-1-4, and on an exposed site the uplift on a lightweight unit is what the anchors are resisting, so the base design has to know what the anchors are going into. The second is drainage fall: the base should fall away from the unit, not towards it, and the roof downpipe outlet should be able to reach the ground without crossing the access side.

2. The lift: decided on weight at radius, not on the product name

Nothing about the delivery is one heavy box. The unit arrives flat-packed, so what gets lifted on site is frame sections and bundles of panels, and that changes the equipment question completely.

A crane is not automatically required. A telehandler with forks will place frame sections and panel bundles where the ground is firm and the reach is short, and it is usually the cheaper route on a site that already has one. A crane earns its cost where the unit has to go over an obstruction, beyond the reach of a telehandler, or into a tight yard. The decision is made on the load chart at the actual working radius, using the unit weight from the packing list: a chart figure for the machine's nominal capacity says nothing about what it can pick up at eight metres.

Handling practice for the container itself follows ISO 3874, which covers the handling and securing of series 1 freight containers, and it is the reason a container is lifted at its corner fittings and never slung under its floor. For a bolted frame the equivalent rule is that the lifting points are the ones shown on the assembly drawing, and no panel edge, purlin or roof sheet is a lifting point whatever it looks like.

3. Bolt-up: square first, torque second

The frame is hot-dip galvanised steel with bolted detachable connections. Galvanising for structural steel is specified under ASTM A123 or EN ISO 1461 depending on the market, and the practical consequence on site is that the coating is the corrosion protection: a member that gets drilled or cut for a site change has a bare edge until it is repaired with a zinc-rich product, and that repair belongs in the same day's work.

The sequence on the drawing is not a suggestion. A partly bolted frame has very little stiffness, so the order in which the frame is closed up decides whether the unit comes out square.

  1. Set out and shim. Land the first frame section on its marked position on the base, pack and shim to level, and check the diagonals of the footprint. Equal diagonals mean square; unequal means the section is racked, and no amount of tightening will pull it back.
  2. Bolt snug, then close the frame. Bring the connections up finger-tight and snug so the frame can still move, add the remaining sections and the twin-unit joint if there is one, and only then go round with the torque wrench.
  3. Torque to the schedule. The bolt grade, the washer arrangement and the torque value come from the assembly drawing. Galvanised connections behave differently from plain ones, and a torque value invented on site is a connection that either slips or strips.
  4. Re-check level and square. After torquing, not before. A frame that has been pulled into position by its bolts will show it here.
  5. Envelope. Panels fix into the frame profiles, joints are sealed, doors and windows are hung and adjusted. The single-slope roof goes on with its fall in the direction shown on the drawing, which is the mistake worth checking twice: a reversed fall is a roof that has to come off.

One sequencing rule covers most of the risk on a small site: do not leave a unit half-panelled and unbraced overnight in wind. Either close the envelope or leave the frame in a state the drawing calls stable.

4. Services: the part a local tradesman signs off

The unit arrives with its internal electrics installed: surface conduit, sockets and switches per the unit layout, and a bathroom pod with pre-fitted plumbing where one is specified. What stays on site is the connection from the unit to the site's own networks, and that is local work done to local rules.

We supply the unit's internal services and the drawings for the connection; we do not sign the local electrical certificate, and no supplier outside the country can.

Site readiness checklist before the container is opened

Everything on this list can be done while the unit is on the water. Everything left undone becomes a delay with a crew standing on it.

What to have in place before the units are unpacked
ItemReady whenWhy it matters
BaseBuilt, level to the supplier's tolerance, draining away from the footprint, anchors in placeThe frame cannot be pulled square on an out-of-level base, and re-doing it after bolt-up is demolition work
Lifting equipmentBooked for the delivery date, load chart checked against the unit weight at the working radiusThe most common single day lost on an installation
Drawings and packing listPrinted and on site, assembly drawing plus bolt schedule plus panel layoutThe sequence and the torque values are on the drawing, not in an email
ToolsImpact driver, torque wrench, level, string line, sealant gun, zinc-rich repair aerosolOne missing tool stops a whole operation, and the repair aerosol is the one always forgotten
CrewAgreed size, briefed on the sequence, fall protection available if anyone works at heightUnder OSHA 29 CFR 1926.501(b)(1) fall protection is required from 6 ft (1.8 m) above a lower level; local rules differ, the principle does not
Power and water at the boundaryAvailable, with the connection point agreedCommissioning cannot start without them, and it is on the critical path at the end
Storage and weatherPanel bundles stored flat, off the ground, weighted or strapped against windA panel bundle is a sail, and damaged panels are a re-order with a sea freight lead time
Permits and inspectionBooked if the project requires one, before work startsAn inspector who arrives to a closed envelope and no records is a second visit

What to ask the supplier before the order is confirmed

Six items, all of which are documents rather than opinions, and all of which should arrive with the quotation or the order confirmation:

  1. The assembly drawing and the bolt schedule. Sequence, bolt grade and torque values. Without these the crew is improvising.
  2. The unit weight and the lifting points. The input to the crane or telehandler selection.
  3. The level tolerance for the base. The number the groundworks contractor builds to.
  4. The panel's fire classification report. Reaction to fire is classified under EN 13501-1 on a tested build-up, and the classification belongs to that build-up, not to the word “rock wool” on the data sheet.
  5. A crew-and-hours schedule per unit. Frame, envelope and fit-out separated, with the operations that assume a crane flagged.
  6. What installation support covers. Drawings only, remote support, or a supervisor on site for the first unit: three different prices and three very different risk profiles.

How those documents are checked before dispatch is described on our inspection page, and the ones a project can request as a package are listed under certifications.

Where the other guides fit

This page covers the site work. The dimensions the base and the lift are worked out from are on the container house size guide, which separates the external envelope from the internal clear size and the wall build-up between them. The cost side, including what a quote usually leaves out such as foundation, crane hire and clearance, is on the container house cost guide.

If the project is a flat-pack or expandable unit rather than a standard detachable, the fixing sequence is different and the flat-pack and expandable range carries the details. Send the site plan, the unit count and the destination, and the reply comes back with the loading plan, the weight and the assembly drawing. Send drawings and the destination, or use the contact page.

Frequently asked questions

Does a detachable container house need a crane to install?

It needs lifting equipment, but not necessarily a crane. The frame is delivered flat-packed, so the loads on site are frame sections and panels rather than a finished room, and a telehandler with forks can handle them where the ground and access allow. A crane is quicker where the unit has to be placed beyond the reach of a telehandler, or where the site is tight. Either way the choice is made on the load chart at the actual radius, using the unit weight from the packing list, not on a nominal tonnage.

Can a detachable container house be assembled without welding?

Yes, and that is the point of the detachable design. Panels bolt to a hot-dip galvanised steel frame through bolted detachable connections, with no site welding on the structure. No welding means no welder, no hot work permit for the structure, no fire watch and no site-applied paint over a weld. Where a galvanised member has to be cut or drilled on site, the cut edge is repaired with a zinc-rich product according to the coating standard rather than left bare.

What foundation does a detachable container house need?

A base that carries the load, keeps the frame in one plane and drains water away from the floor. In practice that is cast-in-situ pad or strip footings, precast blocks, or screw piles, chosen against the ground conditions under EN 1997-1. The two numbers the base design needs are the unit weight and the imposed floor load, both of which come from the supplier for the specific unit, and neither of which should be guessed from the product name. A slab is convenient but it is not the only option, and on a temporary site it is often the wrong one.

How long does it take to assemble a detachable container house?

It depends on the unit count, the fit-out level, the crew size and how much of the work is panel fixing against how much is services connection, so a single figure quoted without those four would be a guess. What can be asked for, and should be, is a crew-and-hours schedule per unit from the supplier: how many people, how many hours per unit for frame, envelope and fit-out separately, and which of those operations assume a crane on site. That schedule is what a local contractor prices against.

Can local labour assemble it, or does it need the supplier's crew?

Local labour can do it, and most export orders are assembled that way, provided the assembly drawing, the packing list and the bolt schedule are on site and someone on the crew can read a drawing. The risk is not skill, it is sequence: a bolted frame that is half assembled is not braced, and a roof sheet fixed before the fall of the single-slope roof has been checked against the drawing has to come off again. If the crew has not built one before, a supplier supervisor for the first unit is usually cheaper than the rework.

Can two detachable units be joined into one larger room?

Yes. Two units can be bolted together along a shared side to make a larger floor area, which is how a canteen or a classroom is usually built from standard units. The joint is a line of bolts between the two frames, and both floors have to be at the same level before the joint is closed, so the base under a twin unit is one base set out for both footprints, not two bases built independently. Anything beyond a side-by-side joint, such as stacking, is a structural question that has to be answered by the frame design for that project.

What has to be on site before the container is opened?

The base, built and level and draining away from the unit; the lifting equipment, booked with its load chart checked against the unit weight; the assembly drawing and the packing list; a crew with an impact driver, a torque wrench, a level, a string line and sealant; power and water available at the boundary for the services connection; and the local inspection booked if the project needs one. Opening a container of panels onto an unprepared site is how panels get damaged and fixings go missing.

Sources

The footprint figures in the table above are the published external sizes multiplied out, and can be recomputed from the dimensions printed beside them. No assembly hours, crew size or lifting capacity is published on this page: those follow the unit count, the fit-out and the machine, and a number written without them would be out of date before the container sailed.